proj16.Office.Microsoft.Policies.Windows• User
Work is entered in
Specifies the default unit of time (minutes, hours, days, weeks, or months) used in the Work field in the current project. If you enable this setting, whenever Project displays work values, the unit you specified will be used. If you disable or do not configure this setting, the user's default setting is used.
Policy Details
- Policy Name
- L_PjWorkUnits
- Registry Key
- software\policies\microsoft\office\16.0\ms project\options\scheduling
- Supported On
- At least Windows Server 2008 R2 or Windows 7
- Available Languages
- en-us
Configuration Elements
Work is entered in
Type: enum
Allowed Values
- 3 Minutes
- 5 Hours
- 7 Days
- 9 Weeks
- 11 Months