ADMX Viewer
proj16.Office.Microsoft.Policies.Windows• User

Actual costs are always calculated by Microsoft Project

Specifies that Project calculates actual costs automatically, based upon resource rates, per-use resource costs, and fixed task costs. If you enable this setting, Project will automatically calculate actual costs. If you disable or do not configure this setting, the user's default setting is used.

Policy Details

Policy Name
L_PjActualCostsCalc
Registry Key
software\policies\microsoft\office\16.0\ms project\options\calculation
Value Name
actual costs are always calculated by microsoft office project
Supported On
At least Windows Server 2008 R2 or Windows 7
Policy State Values
Enabled: 1
Disabled: 0
Available Languages
en-us