Edits to total actual cost will be spread to the status date
Distributes the changes to total actual cost evenly across the schedule to the status date (or to the current date if you have not specified a project status date). If you enable this setting, Project will distribute edits to actual cost evenly across a task up to the status date. If you disable or do not configure this setting, the user's default setting is used.
Policy Details
- Policy Name
- L_PjEditToTotalSpread
- Registry Key
- software\policies\microsoft\office\16.0\ms project\options\calculation
- Value Name
- edits to total actual cost will be spread to the status date
- Supported On
- At least Windows Server 2008 R2 or Windows 7
- Policy State Values
- Enabled: 1Disabled: 0