ADMX Viewer
proj16.Office.Microsoft.Policies.Windows• User

Edits to total task % complete will be spread to the status date

Distributes the changes to total percent complete evenly across the schedule to the project status date (or to the current date if you haven't specified a project status date). If you enable this setting, edits to total task percent complete are evenly distributed across the schedule up to the status date. If you disable or do not configure this setting, the user's default setting is used.

Policy Details

Policy Name
L_PjEditstoTotalTask
Registry Key
software\policies\microsoft\office\16.0\ms project\options\calculation
Value Name
edits to total task %complete will be spread to the status date
Supported On
At least Windows Server 2008 R2 or Windows 7
Policy State Values
Enabled: 1
Disabled: 0
Available Languages
en-us