Inserted projects are calculated like summary tasks

Specifies that a single critical path is calculated throughout the master project, by treating inserted projects as summary tasks in the master project. If you enable this setting, the critical path is calculated by treating inserted projects as summary tasks. If you disable or do not configure this setting, the user's default setting is used.

Policy Details

Policy Name
L_PjInsertedProjects
Registry Key
software\policies\microsoft\office\16.0\ms project\options\calculation
Value Name
inserted projects are calculated like summary tasks
Supported On
At least Windows Server 2008 R2 or Windows 7
Policy State Values
Enabled: 1
Disabled: 0