Move end of completed parts after status date back to status date

Moves the completed portion of a task back to finish at the status date. If you enable this setting, the completed portion of the task moves back to finish at the status date. If you disable or do not configure this setting, the user's default setting is used.

Policy Details

Policy Name
L_PjMoveCompleted
Registry Key
software\policies\microsoft\office\16.0\ms project\options\calculation
Value Name
movecompleted
Supported On
At least Windows Server 2008 R2 or Windows 7
Policy State Values
Enabled: 1
Disabled: 0