ADMX Viewer
proj16.Office.Microsoft.Policies.Windows• User

Show that tasks have estimated durations

Displays a question mark (?) after the duration unit of any task with an estimated duration. If you enable this setting, tasks with estimated durations have a question mark after their duration unit. If you disable or do not configure this setting, the user's default setting is used.

Policy Details

Policy Name
L_PjShowEstimatedDurations
Registry Key
software\policies\microsoft\office\16.0\ms project\options\scheduling
Value Name
show estimated durations
Supported On
At least Windows Server 2008 R2 or Windows 7
Policy State Values
Enabled: 1
Disabled: 0
Available Languages
en-us