Updating task status updates resource status

Automatically updates resource status, such as actual and remaining work and cost, whenever you update task status, such as percent complete, actual duration, or remaining duration. If you enable this setting, task status updates are automatically applied to resources. If you disable or do not configure this setting, the user's default setting is used.

Policy Details

Policy Name
L_PjUpdatingTask
Registry Key
software\policies\microsoft\office\16.0\ms project\options\calculation
Value Name
auto track resources
Supported On
At least Windows Server 2008 R2 or Windows 7
Policy State Values
Enabled: 1
Disabled: 0